Monday, July 03, 2006

H2, Oh!



Click for the Board of Selectmen meeting minutes for August 2, 2004.
BOS meeting -- August 2, 2004

"Hall School/Center School Water Systems Connie Berglund reported to First Selectman Eldredge that Hall School will be getting a new well and that they will throttle back the old well."


Click for the Board of Selectmen meeting minutes for December 20, 2004.
BOS meeting -- DEC.20, 2004

"First Selectman Eldredge commented that Dr. Berglund told me that she was going to satisfy the 2 consent orders that were against the school, basically she did not have anything with water quality, she had the well problem being to much output. At that time she said she was going to throttle back one well and drill a new well to satisfy the consent order. Her feeling now is that her ultimate goal is to bring in public water from Tolland and for that they will need State funding, a rough estimate is $400,000-500,000 to do that but she still wants the funds to be able to satisfy the consent order. She is waiting for evaluations from 4 engineers."


Click for the Board of Selectmen meeting minutes for July 18, 2005.
BOS meeting -- JULY 18, 2005
"First Selectman Eldredge commented that we could go after STEAP to bring water lines over Depot Road to Rt. 32 to Hall School for around $300,000. Selectman Eldredge commented that he suggests we write a proposal for that and that the Housing Authority write a proposal for $200,000 for the water system for the cottages. Selectman Patton asked if our project was funded last year? First Selectman Eldredge commented no but they gave us $150,000 left over. Selectman Patton asked what does Dr. Berglund think? First Selectman Eldredge commented that she likes the idea.

FIRST SELECTMAN ELDREDGE MOVED THAT WE APPLY FOR A STEAP GRANT FOR $300,000 TO DO THE HALL MEMORIAL SCHOOL WATER LINES ONCE BIRMINGHAM UTILITIES BRING IT TO RIVERS EDGE CONDOMINIUMS.
Selectman Blessington seconded the motion.
VOTE: 2 YES (ELDREDGE & BLESSINGTON) 1 ABSTAIN (PATTON)
Selectman Patton commented that he does not think we should vote on this tonight, we need to discuss everything."


Click for the Board of Selectmen meeting minutes for February 21, 2006.
BOS meeting -- FEB. 21, 2006

"First Selectman Eldredge approached BU regarding extending the water to Hall School. It might be the most economic and the best way to fix the problem. Hall School is regulated by the Health Dept. Cam Walden commented that the DPH looked at lots of schools in CT for violations and deficiencies. Hall School has only one well and that does not have enough separation from the fuel tank, you must have two wells. They lack sufficient storage, they need controls on the existing well, there is an iron problem and the water quality does not meet State standards. It is an operational headache for the school. Mr. Walden commented that it is certainly worth looking at Birmingham Utilities solution. The Town of Tolland has sufficient supply and good quality.

Selectman Lewis asked is there enough contingency in the $300,000? Mr. Keefe replied yes. Selectman Lewis asked you will not know the exact price until we give you the go ahead? Mr. Keefe commented we don’t know about ledge. Selectman Patton asked do you have an estimate? Mr. Keefe commented the number is conservative. Selectman Patton commented that I thought I read in the letter that it would be $300,000 no mater what. We need all the cost associated with this project. Further discussion on the cost followed. First Selectman Eldredge commented we asked BU for the construction cost, the engineering cost and contingency to come up with the $300,000. Selectman Lewis commented we need to know up front what it will cost."

Click for the Board of Selectmen meeting minutes for March 6, 2006.

BOS meeting -- March 6, 2006

PRESENT TO SPEAK
"L. Semprebon, Chair, BOE, asked if the Board received the figures they wanted on the Hall School water system. Selectman Patton commented that they did and noted that the $70,000 for hookup should be included.
Selectman Patton also suggested that the BOE begin the paperwork to do their part. You may want to put the paperwork together for the Dept. of Education. You need to get approval before you can start the project. First Selectman Eldredge commented we are still waiting to see if we get the grant."


Compare the above from the 03-06-06 BOS meeting minutes with this audio clip of the Present to Speak segment of the meeting:

Click for the audio clip of the Present to Speak segment of the 03-06-06 BOS meeting (mp3 -- 253kb)


H2 Oh, to Go

Click the photo to load and play (wmv -- 2.1mb).